Bangabandhu Jamuna Multipurpose Bridge opened in June
1998, is the longest bridge in Bangladesh as well as in South Asia, and
the 11th longest bridge in the world. It was constructed over the river
jamuna,
mightiest of the three major rivers of Bangladesh, and fifth largest in
the world in terms of volumetric discharge. The bridge established a strategic
link between the eastern and western parts of Bangladesh. It generates
multifarious benefits for the people and especially, promotes inter-regional
trade in the country. Apart from quick movement of goods and passenger
traffic by road and rail, it facilitated transmission of electricity and
natural gas,
and integration of telecommunication
links.
The bridge, stretching from tangail
to sirajganj
is located on the Asian Highway and the Trans-Asian Railway which,
when fully developed, will provide uninterrupted international
road and railway
links from South-east Asia to North-west Europe.
|
|
Bangabandhu Jamuna Multipurpose
Bridge
|
The bridge was constructed at a cost of $962 million.
The cost of construction was shared by IDA, ADB, OECF of Japan, and the
government of Bangladesh. Of the total, IDA, ADB and OECF supplied 22%
each, and the remaining 34% was borne by Bangladesh. The components of
the project's cost were: bridge and viaducts - $269 million (28%); river
training works - $323 million (35%); roads and embankments - $71 million
(7%); consultancy - $33 million (3%); land, resettlement and environment
- $67 million (7%); establishment - $13 million (1%) and others - $186
million (19%).
Considering the fact that the width of the main channel
does not exceed 3.5 km, and after making allowances for floods,
a bridge length of 5 km was considered adequate. In October 1995, one
year after the commencement of physical work of the bridge, a bridge length
of 4.8 km, instead of a flood-width of the river at 14 km, was finalised.
This narrowing was essential to keep the overall project cost within economic
viability. It has, however, required considerable river training work
to keep the river under the bridge.
To withstand predicted scourge and possible earthquakes,
the bridge is supported on 80-85 m long and 2.5 m and 3.15 m diameter
steel piles, which were driven by powerful (240-ton) hydraulic hammer.
The superstructure of the bridge is pre-cast segments erected by the
balanced cantilever method. Basic features of the bridge are: length
(main part) - 4.8 km; width - 18.5 metre; spans - 49; deck segments -
1263; piles - 121; piers - 50; road lanes - 4; railway tracks - 2.
The
people and the successive governments in this part of the subcontinent
always longed to bridging the mighty Jamuna and thereby integrate the
communication systems of the region. Popular leader abdul hamid khan bhasani first
raised the demand for construction of the Jamuna bridge at a political
level in 1949. In the 1954 provincial elections of East Pakistan, the
21-point manifesto of the united front contained a demand for the bridge. On 6 January 1964, Mohammad Saifur Rahman, a member from rangpur
in the Provincial Assembly inquired about government's intentions with
regard to the construction of a bridge over the Jamuna. On 11 July 1966,
Shamsul Haque, another member from Rangpur in the same Assembly, moved a
resolution for the construction of the bridge and the house adopted it
unanimously.
Accordingly, a preliminary
feasibility study was carried out in 1969 by Freeman Fox and Partners of
UK. They recommended a rail-cum-road bridge near Sirajganj with an
estimated cost of $175 million. The estimates were preliminary in nature
and a more detailed study was recommended. On the other hand, in his
address to the nation over radio and television on the eve of general
election in Pakistan in 1970, the awami league leader sheikh mujibur rahman
mentioned the construction of Jamuna Bridge as an election pledge of
his party. But all efforts were interrupted due to political unrest and
liberation war.
After the independence of
Bangladesh, the new government publicly stated its intention in 1972 to
construct a bridge over the Jamuna and budgetary provisions were kept
for the purpose in the 1972-73 budget. On being invited by the
Bangladesh government, the Japanese International Cooperation Agency
(JICA) undertook a feasibility study in 1973 on the construction of a
road-cum-rail bridge over the Jamuna.
The JICA
study, completed in 1976, concluded that the Jamuna project would cost
$683 million with an economic rate of return (ERR) of only 2.6%.
Considering that the project is not technically and economically viable,
the government had abandoned the project. The government had, however,
revived it later in 1982 and commissioned a new study to determine the
feasibility of transferring natural
gas to western parts of the country across the Jamuna. The study
concluded that an independent gas connector was not economically viable.
However, the consultants made an assessment of the engineering
feasibility and cost of a combined road-cum-gas transmission bridge,
which introduced the concept of a multipurpose bridge. It was estimated
that a 12-km long bridge with three road lanes would cost $420 million.
Upon consideration of the report, the cabinet made a decision to take
immediate steps in pursuit of the project.
The
Jamuna Multipurpose Bridge Authority (JMBA) was set up by an ordinance
promulgated by the President on 3 July 1985 to implement the project.
For mobilisation of domestic resources, another ordinance was
promulgated by which a Jamuna Bridge surcharge and levy were introduced.
A total of Tk 5.08 billion was mobilised in the process till its
abolition.
In 1986, phase-I feasibility study for the bridge was
carried out when the site between Sirajganj and Bhuapur (Tangail) was
found to be the best. Between 1987 and 1989, the phase-II feasibility
study was carried out when a road-cum-rail-cum-power bridge was found
both economically and technically viable. Funding arrangements for the
bridge were finally made with IDA, ADB and OECF of Japan by the government
of Bangladesh in 1992. Tenders were invited through international bidding
for construction contracts in 1993. Contracts for the bridge, river training
works and two approach roads were awarded in March 1994. The foundation
stone of the bridge was laid on 10 April 1994. Physical implementation
of the project commenced on 15 October 1994, and all the components except
gas transmission line were completed by June 1998. The bridge was opened
for traffic on 23 June 1998.
No comments:
Post a Comment